Construction Phase
January 2025 - January 2027
Key Points
Continued engagement with stakeholders and community leaders
Searching for additional funding opportunities for the construction phase
Coordination and partnering with the utility (Pacific Power)
Equipment procurement
Labor, construction oversight contracting
Legal, financial, oversight contracting
Additional risks with the main one being funding
Pre-Development & Engineering Phase
November 2023 - November 2024
Key Points
Continued engagement with stakeholders and community leaders
Interconnection may be a risk
Compatibility check for microgrid technologies
Searching for additional funding opportunities for the construction phase
Conducting coordination and partnering with the utility (Pacific Power)
Line up contractors and technology before the Construction Phase
Planning Phase
January 2023 - October 2023
Key Points
Engaging with the community leaders and stakeholders through the development of a Community Energy Strategic Plan.
Finalizing list of county critical infrastructure, shelters, facilities, etc.
ProtoGen has begun the electrical modeling of the microgrid
Searching for additional funding opportunities for engineering and construction
Conducting outreach and partnering with the utility (Pacific Power)